By Tuesday 21st February
Jebson's have done a little more stone work to the front extension but have also pulled the inner walls of the gable end down ready for one of the six lengths of steel used in the structure of the house. So at the moment the floor and roof are being held up by accrow's and the steel should be fitted today (22nd Feb).
 |
The big hole in the gable end |
 |
This beam 203 x 203 x 46 UC will help hold it all up |
 |
The view into the original bedrooms. |
 |
And the view from the bedrooms outside |
 |
And another view from the original small bedroom |
 |
The steel beam painted and ready to fit. |